STARTING OUT WITH BARE LAND
PERMITS-PLACEMENT, ELECTRIC, ENCROACHMENT, LDAP, SDC. DEPENDING ON AREA THIS CAN TAKE ANYWHERE FROM 2-8 WEEKS.
SITE WORK-EXCAVATION, CONCRETE RUNNERS, ETC.
7-10 DAYS
DELIVERY
SET THE HOME
3-7 DAYS
UTILITIES-WATER, ELECTRIC, PHONE AND CABLE
2-3 DAYS
INSPECTIONS
SKIRTING
START ON GARAGE, PATIO, DECKS AND DRIVEWAYS.
ENERGIZE
2-3 DAYS
TAPE AND TEXTURE
3-5 DAYS
CARPET
1-2 DAYS
CLEANING
1 DAY
THEN THE FINAL GRADING, LANDSCAPE, IRRIGATION, HEAT PUMP (IF APPLICABLE) AND THE FENCIGN.
AFTER PERMITS ARE ISSUED, AND DEPENDING ON THE CONTRACTOR THIS PROCESS CAN BE ANYWHERE FROM 30-90 DAYS