Time Frame

Fuqua Homes STARTING OUT WITH BARE LAND

PERMITS-PLACEMENT, ELECTRIC, ENCROACHMENT, LDAP, SDC. DEPENDING ON AREA THIS CAN TAKE ANYWHERE FROM 2-8 WEEKS.

SITE WORK-EXCAVATION, CONCRETE RUNNERS, ETC.
7-10 DAYS

DELIVERY

SET THE HOME
3-7 DAYS

UTILITIES-WATER, ELECTRIC, PHONE AND CABLE
2-3 DAYS

INSPECTIONS

SKIRTING

START ON GARAGE, PATIO, DECKS AND DRIVEWAYS.

ENERGIZE
2-3 DAYS

TAPE AND TEXTURE
3-5 DAYS

CARPET
1-2 DAYS

CLEANING
1 DAY

THEN THE FINAL GRADING, LANDSCAPE, IRRIGATION, HEAT PUMP (IF APPLICABLE) AND THE FENCIGN.

AFTER PERMITS ARE ISSUED, AND DEPENDING ON THE CONTRACTOR THIS PROCESS CAN BE ANYWHERE FROM 30-90 DAYS